Building Regulations: Solid Wall

Where a solid wall has been upgraded by the installation of insulation it must meet the minimum energy efficiency values set out in the Approved Documents.

However, if such an upgrade is not technically or functionally feasible, the element should be upgraded to the best standard which can be achieved within a simple payback of no greater than 15 years.

Where 25 per cent or more of an external wall is being renovated building regulations would normally apply, and the thermal insulation of the wall would have to meet the standards required by building regulations Approved Documents. In this context renovation means the provision of a new layer or the replacement of an existing layer, but excludes decorative finishes.

Related Links:

Find a Trade Professional

Use our partner directories to find a planning or building professional to help with your project or development.

Find a professional


Useful links

Make an application Studio Charrette planning consultancy calculator Sell your site with Land Match
    1. https://www.planningportal.co.uk/permission/common-projects/external-walls/building-regulations
    2. https://www.inca-ltd.org.uk/

    The Planning Portal is delivered by PortalPlanQuest Limited which is a joint venture between TerraQuest Solutions Limited and the Ministry of Housing, Communities & Local Government (MHCLG). All content © 2024 Planning Portal.

    The Planning Portal is delivered by PortalPlanQuest Limited which is a joint venture between TerraQuest Solutions Limited and the Ministry of Housing, Communities & Local Government (MHCLG). All content © 2024 Planning Portal.